Overview
This document provides a detailed construction timeline for Luxa Salon Suites build-out, covering pre-construction through Certificate of Occupancy. Based on Phase 9 research, the total project duration ranges from 13 weeks (optimistic) to 22 weeks (realistic with contingencies).
Timeline Assumptions:
- 18-suite facility, ~3,500-4,000 sq ft
- Loudoun County jurisdiction
- Standard tenant improvement (non-structural)
- No hazardous material abatement required
1. Timeline Overview
Master Schedule (Gantt-Style)
WEEK: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
PRE-CONSTRUCTION
[====DESIGN/BIDDING====]
[----EQUIPMENT ORDER (China: 45+ days)---------------------------------->]
[DELIVERY]
PERMITS
[====SUBMIT====][====REVIEW====][RESUBMIT][====REVIEW====][ISSUE]
(if needed)
CONSTRUCTION
[DEMO][FRAME/ROUGH][DRYWALL][FINISH][TRIM]
|----------- 6-10 WEEKS -----------|
CLOSEOUT
[INSPECT][CO]
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
WEEK: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Phase Duration Summary
| Phase | Duration | Weeks | Dependencies | Notes |
|---|
| Pre-Construction | 2-4 weeks | W1-W4 | Lease signed | Design, bidding, ordering |
| Permits | 3-6 weeks | W2-W8 | Plans complete | May overlap with pre-con |
| Construction | 6-10 weeks | W6-W16 | Permit issued | Core build-out work |
| Closeout | 2 weeks | W16-W18 | Construction complete | Inspections, CO |
| TOTAL | 13-22 weeks | - | - | Plus contingencies |
2. Pre-Construction Phase (Weeks 1-4)
Week 1: Design Kickoff
| Day | Activity | Owner | Deliverable |
|---|
| 1-2 | Finalize floor plan with architect | Owner + Architect | Preliminary floor plan |
| 2-3 | Review suite mix and placement | Owner | Confirmed layout |
| 3-4 | MEP engineer coordination | Architect | MEP requirements |
| 4-5 | Create Scope of Work document | Owner | SOW ready for distribution |
Milestones:
Week 1-2: Contractor Bidding
| Day | Activity | Owner | Deliverable |
|---|
| 5-7 | Distribute SOW to contractors (minimum 3) | Owner | Bid packages sent |
| 7-10 | Site walk-through with bidders | Owner + Contractors | Questions addressed |
| 10-12 | Bidder questions due | Contractors | RFI responses |
| 12-14 | Addenda issued (if needed) | Owner | Clarifications |
Contractor Bid Timeline:
- Bid period: 7-10 days
- Minimum bidders: 3 (recommended)
- Site visit: Required before bid
Week 2-3: Bid Review and Selection
| Day | Activity | Owner | Deliverable |
|---|
| 14-15 | Bids due | Contractors | Completed bid forms |
| 15-17 | Review and compare bids | Owner | Bid comparison matrix |
| 17-19 | Interview top 2 contractors | Owner | Selection criteria evaluation |
| 19-21 | Select contractor | Owner | Award notification |
| 21-23 | Contract negotiation | Owner + Contractor | Final contract terms |
Selection Criteria:
- Price (40%)
- Schedule (20%)
- Experience with similar projects (20%)
- References (10%)
- Completeness of bid (10%)
Week 3-4: Long-Lead Equipment Orders
| Item | Lead Time | Order By | Supplier |
|---|
| China FF&E (chairs, mirrors, carts) | 45-60 days | Week 3 | Alibaba Trade Assurance |
| Shampoo bowls (US) | 2-3 weeks | Week 4 | Keller, AGS, or SSW |
| Cabinetry | 3-4 weeks | Week 4 | Local or Kaemark |
| Electronic locks | 2-3 weeks | Week 4 | Nexkey or ButterflyMX |
| Lighting fixtures (CRI 90+) | 2-3 weeks | Week 4 | Electrical supplier |
China Equipment Order Process:
- Finalize product selections
- Order samples if not already received
- Place bulk order via Trade Assurance
- Schedule pre-shipment inspection (AQL 2.5/4.0)
- Confirm shipping/delivery timeline
Week 2: Permit Application
| Activity | Timeline | Notes |
|---|
| Complete permit drawings | Week 1-2 | Architect + engineer |
| Submit via LUN system | Day 10 | Loudoun online submission |
| Pay permit fees | Day 10 | At submission |
Loudoun County Permit Resources:
- LUN online portal (required since Dec 2025)
- EZ Tenant Permit (if eligible: <7,500 sf, non-structural)
- Plan review: ~10 business days per cycle
3. Permit Phase (Weeks 2-8)
Permit Timeline Detail
| Week | Activity | Expected Outcome |
|---|
| W2 | Submit permit application via LUN | Application received |
| W3-W4 | First plan check review | Comments within ~10 business days |
| W4 | Address plan check comments | Revisions prepared |
| W4-W5 | Resubmit if needed | Second submittal |
| W5-W7 | Second review (if required) | Approval or additional comments |
| W6-W7 | Fire Marshal coordination | Fire safety approval |
| W7-W8 | Permit issuance | Building permit in hand |
Plan Check Comment Categories
| Category | Typical Comments | Response Time |
|---|
| Fire/Life Safety | Egress, sprinklers, exits | Must address |
| Mechanical | HVAC sizing, ventilation | Must address |
| Electrical | Load calc, panel sizing | Must address |
| Plumbing | Fixture count, venting | Must address |
| ADA | Clearances, heights | Must address |
| Structural | Usually N/A for TI | If applicable |
Fire Marshal Coordination
| Activity | When | Notes |
|---|
| Initial review | With permit submittal | Fire Marshal on distribution |
| Pre-construction meeting | Week 5-6 | Recommended for salon use |
| Interim inspections | During construction | As required |
| Final inspection | Before CO | Required for occupancy |
Fire Marshal Concerns for Salon Suites:
- Sprinkler coverage in new walls
- Exit signage and emergency lighting
- Egress path compliance
- Chemical storage (nail services)
4. Construction Phase (Weeks 6-16)
Construction Schedule by Week
Weeks 6-7: Demolition and Site Prep
| Activity | Duration | Notes |
|---|
| Mobilization | 1 day | Contractor setup |
| Protection of existing elements | 1 day | Protect what stays |
| Demolition of existing partitions | 2-3 days | If applicable |
| Debris removal | 1-2 days | Haul-off |
| Layout and marking | 1 day | Establish suite locations |
Deliverable: Space cleared and ready for framing
Weeks 7-9: Rough-In Work
Framing (Week 7-8):
| Activity | Duration | Notes |
|---|
| Metal stud framing | 4-5 days | All suite walls |
| Door frame installation | 1-2 days | 18 suites + common |
| Bulkheads/soffits | 1-2 days | As needed |
| Blocking for fixtures | 1 day | Mirror, cabinet mounts |
Rough Electrical (Week 7-8):
| Activity | Duration | Notes |
|---|
| Panel installation | 1 day | 200A panel |
| Branch circuit rough | 3-4 days | All circuits |
| Outlet box installation | 2 days | Per suite requirements |
| Lighting rough | 2 days | Boxes and feeds |
Rough Plumbing (Week 8-9):
| Activity | Duration | Notes |
|---|
| Drain rough-in | 2-3 days | Below slab if needed |
| Supply rough-in | 2 days | Hot and cold |
| Water heater | 1 day | Set and connect |
| Vent connections | 1 day | Per code |
HVAC Rough (Week 8-9):
| Activity | Duration | Notes |
|---|
| Ductwork | 3-4 days | Supply and return |
| Equipment setting | 1-2 days | AHU or mini-splits |
| Exhaust rough | 1 day | Restrooms, laundry |
Milestone: Rough-In Inspection (End of Week 9)
- Schedule trade inspections
- Must pass before drywall
- Payment trigger: 30%
Weeks 9-11: Insulation and First Drywall
| Activity | Duration | Notes |
|---|
| R-13 insulation installation | 2-3 days | All suite walls |
| First drywall layer (base) | 3-4 days | Both sides of all walls |
| Acoustic sealant application | 1 day | All perimeters |
Critical STC 48-52 Requirements:
Weeks 11-12: Green Glue and Second Drywall
| Activity | Duration | Notes |
|---|
| Green Glue application | 2 days | 2 tubes per 4x8 sheet |
| Second drywall layer (face) | 3-4 days | Both sides of all walls |
| Taping | 2-3 days | First coat |
Critical Requirements:
Weeks 12-13: Drywall Finishing
| Activity | Duration | Notes |
|---|
| Second coat mud | 2 days | All joints |
| Third coat (if needed) | 1 day | Sand and touch-up |
| Sanding | 1-2 days | Smooth finish |
| Texture (if applicable) | 1 day | Per finish spec |
| Prime | 1-2 days | All surfaces |
| Paint | 2-3 days | Two coats |
Weeks 13-14: Flooring Installation
| Activity | Duration | Notes |
|---|
| Subfloor prep | 1-2 days | Level and clean |
| LVP installation (suites) | 3-4 days | 18 suites |
| LVP installation (common) | 1-2 days | Corridors, reception |
| Tile installation (restrooms) | 1-2 days | If tile specified |
| Transitions and trim | 1 day | All thresholds |
Weeks 14-15: MEP Trim and Fixtures
Electrical Trim:
| Activity | Duration | Notes |
|---|
| Outlets and switches | 2-3 days | All devices |
| Lighting fixtures | 2-3 days | Task, ambient, accent |
| Panel labeling | 1 day | Per suite |
Plumbing Trim:
| Activity | Duration | Notes |
|---|
| Shampoo bowls | 2-3 days | 10-12 units |
| Faucets | 1 day | All locations |
| Restroom fixtures | 1-2 days | Toilets, sinks |
| Break room sink | 1 day | Utility sink |
HVAC Trim:
| Activity | Duration | Notes |
|---|
| Diffusers and grilles | 1-2 days | All locations |
| Thermostats | 1 day | Zone controls |
| Exhaust fans | 1 day | Restrooms, laundry |
Cabinetry and Millwork:
| Activity | Duration | Notes |
|---|
| Wall cabinets | 2-3 days | All suites |
| Base cabinets | 1-2 days | Shampoo areas |
| Mirrors | 1-2 days | All styling stations |
Weeks 15-16: Final Touches and Punch List
| Activity | Duration | Notes |
|---|
| Door hardware | 2 days | Smart lock prep (locks separate) |
| Touch-up paint | 1-2 days | All surfaces |
| Cleaning | 1-2 days | Construction clean |
| Punch list walk | 1 day | Owner + contractor |
| Punch list completion | 2-3 days | Address all items |
Milestone: Substantial Completion (End of Week 16)
- All work complete except punch
- Payment trigger: 30%
5. Closeout Phase (Weeks 16-18)
Inspection Schedule
| Week | Inspection | Authority | Notes |
|---|
| W16 | Electrical final | County/Inspector | After all devices complete |
| W16 | Plumbing final | County/Inspector | After all fixtures complete |
| W16 | Mechanical final | County/Inspector | After HVAC complete |
| W17 | Fire Marshal final | Fire Marshal | Required for salon use |
| W17 | Building final | Building Inspector | Comprehensive review |
| W17-W18 | Certificate of Occupancy | I&P | After all finals pass |
Inspection Preparation Checklist
Before Electrical Final:
Before Plumbing Final:
Before Mechanical Final:
Before Fire Marshal Final:
Before Building Final:
Equipment Delivery and Installation (Week 18)
| Activity | Duration | Notes |
|---|
| China equipment receipt | 1 day | Verify against order |
| US equipment receipt | 1 day | Shampoo bowls, etc. |
| Equipment staging | 1 day | Organize by suite |
| Laundry equipment install | 1 day | Washer/dryer hookup |
| Final walkthrough | 1 day | Owner acceptance |
Milestone: Certificate of Occupancy (Week 17-18)
- Legal permission to occupy
- Payment trigger: 10% (final)
- Ready for tenant move-in
6. Critical Path Items
Critical Path Summary
The following items are on the critical path and any delay directly extends the project:
| Item | Start | Duration | Impact if Delayed |
|---|
| Permit application | Week 2 | 3-6 weeks | 1:1 delay to construction |
| China equipment order | Week 3-4 | 45+ days | Tenant move-in delay |
| Fire Marshal coordination | Week 5-6 | Ongoing | CO delay |
| Rough-in inspection | Week 9 | 1-2 days | Drywall delay |
| Building final inspection | Week 17 | 1-2 days | CO delay |
Critical Path Visualization
CRITICAL PATH:
PERMIT APP (W2) -----> PERMIT REVIEW (W2-W8) -----> PERMIT ISSUE (W8)
|
v
CONSTRUCTION START (W8)
|
v
ROUGH-IN COMPLETE (W9)
|
v
INSPECTIONS (W9) -----> PASS
|
v
DRYWALL/FINISH (W9-W16)
|
v
SUBSTANTIAL COMP (W16)
|
v
FINAL INSPECTIONS (W16-W17)
|
v
CO ISSUED (W18)
Float (Non-Critical) Activities
| Activity | Float | Notes |
|---|
| Equipment selection | 2-3 weeks | Can finalize during bidding |
| Furniture procurement | 4-6 weeks | After major decisions |
| Signage | 6-8 weeks | Can complete post-CO |
| IT/Security | 4-6 weeks | Can parallel with construction |
7. Milestone Markers
Payment Milestones
| Milestone | Percentage | Trigger Criteria |
|---|
| Contract Signing | 30% | Executed contract |
| Rough-In Complete | 30% | All rough inspections passed |
| Substantial Completion | 30% | Punch list walk complete |
| Final/CO | 10% | CO issued, punch complete |
Project Milestones
| Milestone | Target Week | Trigger |
|---|
| Lease Executed | W0 | Project start |
| Design Complete | W1-2 | Floor plan and MEP approved |
| Contractor Selected | W3 | Contract signed |
| Permit Submitted | W2 | Application in system |
| China Order Placed | W3-4 | PO confirmed |
| Permit Issued | W6-8 | Building permit in hand |
| Construction Start | W6-8 | Mobilization |
| Rough-In Complete | W9-10 | Inspections passed |
| Drywall Complete | W12-13 | Paint ready |
| Substantial Completion | W15-16 | Walk-through complete |
| Final Inspections | W16-17 | All trades passed |
| CO Issued | W17-18 | Legal occupancy |
| Equipment Delivered | W17-18 | All equipment on site |
| Tenant Move-In Ready | W18-20 | Fully operational |
8. Timeline Scenarios
Optimistic Scenario: 13 Weeks
Assumptions:
- Permit approved first review (no resubmittal)
- No change orders
- Weather/delivery issues none
- Inspections pass first time
| Phase | Duration |
|---|
| Pre-Construction | 2 weeks |
| Permits (parallel) | 3 weeks |
| Construction | 6 weeks |
| Closeout | 2 weeks |
| TOTAL | 13 weeks |
Base Case Scenario: 18 Weeks
Assumptions:
- One permit resubmittal required
- Minor change orders
- Standard inspection process
- China shipping on schedule
| Phase | Duration |
|---|
| Pre-Construction | 3 weeks |
| Permits | 5 weeks |
| Construction | 8 weeks |
| Closeout | 2 weeks |
| TOTAL | 18 weeks |
Realistic/Conservative Scenario: 22 Weeks
Assumptions:
- Two permit resubmittals
- Moderate change orders
- Fire Marshal additional review
- China shipping delay (+2 weeks)
- Weather contingency
| Phase | Duration |
|---|
| Pre-Construction | 4 weeks |
| Permits | 6 weeks |
| Construction | 10 weeks |
| Closeout | 2 weeks |
| TOTAL | 22 weeks |
Timeline Comparison Chart
SCENARIO WEEK: 4 8 12 16 20 24
|---|---|---|---|---|
OPTIMISTIC [=======|====CO====] 13 weeks
|---|---|---|---|---|
BASE CASE [===========|========CO=====] 18 weeks
|---|---|---|---|---|
CONSERVATIVE [================|============CO====] 22 weeks
|---|---|---|---|---|
WEEK: 4 8 12 16 20 24
9. Contingency Planning
Schedule Contingencies
| Risk | Probability | Impact | Mitigation |
|---|
| Permit delay | Medium | 2-4 weeks | Early submission, pre-meeting with I&P |
| China shipping delay | Medium | 2-3 weeks | Order early (Week 3), buffer in schedule |
| Material availability | Low-Medium | 1-2 weeks | Confirm lead times before ordering |
| Weather (delivery) | Low | 1 week | Indoor staging area |
| Inspection failure | Low-Medium | 1 week | Pre-inspection walkthrough |
| Change orders | Medium | 1-3 weeks | Strict change order control |
Built-In Contingency Buffers
| Phase | Base Duration | Buffer | With Buffer |
|---|
| Pre-Construction | 3 weeks | +1 week | 4 weeks |
| Permits | 5 weeks | +1 week | 6 weeks |
| Construction | 8 weeks | +2 weeks | 10 weeks |
| Closeout | 2 weeks | +0 weeks | 2 weeks |
| TOTAL | 18 weeks | +4 weeks | 22 weeks |
Contingency Recommendations
- Permit buffer: Add 2 weeks to permit timeline in all planning
- China shipping buffer: Add 2 weeks to quoted delivery dates
- Weather contingency: Plan deliveries mid-week (avoid Monday/Friday)
- Inspection buffer: Schedule inspections with 2-day cushion
10. Schedule Tracking Template
Weekly Progress Report Format
| Week | Phase | Planned | Actual | Variance | Notes |
|---|
| 1 | Pre-Con | Design kickoff | | | |
| 2 | Pre-Con | SOW distribution | | | |
| 3 | Pre-Con | Contractor selection | | | |
| 4 | Permit | First review expected | | | |
| ... | ... | ... | | | |
Milestone Tracking
| Milestone | Planned Date | Actual Date | Variance | Status |
|---|
| Design Complete | | | | |
| Permit Submitted | | | | |
| Contractor Signed | | | | |
| Permit Issued | | | | |
| Rough-In Complete | | | | |
| Substantial Complete | | | | |
| CO Issued | | | | |
Risk Log
| Risk | Date Identified | Probability | Impact | Mitigation | Status |
|---|
| | | | | |
Construction Timeline Complete - Ready for Site-Specific Scheduling
Phase 9: Build-Out Planning - Plan 01 Task 3 Complete