Construction Timeline

Week-by-week build-out schedule from lease signing to grand opening.

Overview

This document provides a detailed construction timeline for Luxa Salon Suites build-out, covering pre-construction through Certificate of Occupancy. Based on Phase 9 research, the total project duration ranges from 13 weeks (optimistic) to 22 weeks (realistic with contingencies).

Timeline Assumptions:

  • 18-suite facility, ~3,500-4,000 sq ft
  • Loudoun County jurisdiction
  • Standard tenant improvement (non-structural)
  • No hazardous material abatement required

1. Timeline Overview

Master Schedule (Gantt-Style)

WEEK:  1   2   3   4   5   6   7   8   9  10  11  12  13  14  15  16  17  18  19  20  21  22
       |---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
PRE-CONSTRUCTION
       [====DESIGN/BIDDING====]
       [----EQUIPMENT ORDER (China: 45+ days)---------------------------------->]
                                                                               [DELIVERY]

PERMITS
           [====SUBMIT====][====REVIEW====][RESUBMIT][====REVIEW====][ISSUE]
                                           (if needed)

CONSTRUCTION
                                                   [DEMO][FRAME/ROUGH][DRYWALL][FINISH][TRIM]
                                                   |----------- 6-10 WEEKS -----------|

CLOSEOUT
                                                                               [INSPECT][CO]
       |---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
WEEK:  1   2   3   4   5   6   7   8   9  10  11  12  13  14  15  16  17  18  19  20  21  22

Phase Duration Summary

PhaseDurationWeeksDependenciesNotes
Pre-Construction2-4 weeksW1-W4Lease signedDesign, bidding, ordering
Permits3-6 weeksW2-W8Plans completeMay overlap with pre-con
Construction6-10 weeksW6-W16Permit issuedCore build-out work
Closeout2 weeksW16-W18Construction completeInspections, CO
TOTAL13-22 weeks--Plus contingencies

2. Pre-Construction Phase (Weeks 1-4)

Week 1: Design Kickoff

DayActivityOwnerDeliverable
1-2Finalize floor plan with architectOwner + ArchitectPreliminary floor plan
2-3Review suite mix and placementOwnerConfirmed layout
3-4MEP engineer coordinationArchitectMEP requirements
4-5Create Scope of Work documentOwnerSOW ready for distribution

Milestones:

  • Floor plan preliminary complete
  • SOW document finalized

Week 1-2: Contractor Bidding

DayActivityOwnerDeliverable
5-7Distribute SOW to contractors (minimum 3)OwnerBid packages sent
7-10Site walk-through with biddersOwner + ContractorsQuestions addressed
10-12Bidder questions dueContractorsRFI responses
12-14Addenda issued (if needed)OwnerClarifications

Contractor Bid Timeline:

  • Bid period: 7-10 days
  • Minimum bidders: 3 (recommended)
  • Site visit: Required before bid

Week 2-3: Bid Review and Selection

DayActivityOwnerDeliverable
14-15Bids dueContractorsCompleted bid forms
15-17Review and compare bidsOwnerBid comparison matrix
17-19Interview top 2 contractorsOwnerSelection criteria evaluation
19-21Select contractorOwnerAward notification
21-23Contract negotiationOwner + ContractorFinal contract terms

Selection Criteria:

  1. Price (40%)
  2. Schedule (20%)
  3. Experience with similar projects (20%)
  4. References (10%)
  5. Completeness of bid (10%)

Week 3-4: Long-Lead Equipment Orders

ItemLead TimeOrder BySupplier
China FF&E (chairs, mirrors, carts)45-60 daysWeek 3Alibaba Trade Assurance
Shampoo bowls (US)2-3 weeksWeek 4Keller, AGS, or SSW
Cabinetry3-4 weeksWeek 4Local or Kaemark
Electronic locks2-3 weeksWeek 4Nexkey or ButterflyMX
Lighting fixtures (CRI 90+)2-3 weeksWeek 4Electrical supplier

China Equipment Order Process:

  1. Finalize product selections
  2. Order samples if not already received
  3. Place bulk order via Trade Assurance
  4. Schedule pre-shipment inspection (AQL 2.5/4.0)
  5. Confirm shipping/delivery timeline

Week 2: Permit Application

ActivityTimelineNotes
Complete permit drawingsWeek 1-2Architect + engineer
Submit via LUN systemDay 10Loudoun online submission
Pay permit feesDay 10At submission

Loudoun County Permit Resources:

  • LUN online portal (required since Dec 2025)
  • EZ Tenant Permit (if eligible: <7,500 sf, non-structural)
  • Plan review: ~10 business days per cycle

3. Permit Phase (Weeks 2-8)

Permit Timeline Detail

WeekActivityExpected Outcome
W2Submit permit application via LUNApplication received
W3-W4First plan check reviewComments within ~10 business days
W4Address plan check commentsRevisions prepared
W4-W5Resubmit if neededSecond submittal
W5-W7Second review (if required)Approval or additional comments
W6-W7Fire Marshal coordinationFire safety approval
W7-W8Permit issuanceBuilding permit in hand

Plan Check Comment Categories

CategoryTypical CommentsResponse Time
Fire/Life SafetyEgress, sprinklers, exitsMust address
MechanicalHVAC sizing, ventilationMust address
ElectricalLoad calc, panel sizingMust address
PlumbingFixture count, ventingMust address
ADAClearances, heightsMust address
StructuralUsually N/A for TIIf applicable

Fire Marshal Coordination

ActivityWhenNotes
Initial reviewWith permit submittalFire Marshal on distribution
Pre-construction meetingWeek 5-6Recommended for salon use
Interim inspectionsDuring constructionAs required
Final inspectionBefore CORequired for occupancy

Fire Marshal Concerns for Salon Suites:

  • Sprinkler coverage in new walls
  • Exit signage and emergency lighting
  • Egress path compliance
  • Chemical storage (nail services)

4. Construction Phase (Weeks 6-16)

Construction Schedule by Week

Weeks 6-7: Demolition and Site Prep

ActivityDurationNotes
Mobilization1 dayContractor setup
Protection of existing elements1 dayProtect what stays
Demolition of existing partitions2-3 daysIf applicable
Debris removal1-2 daysHaul-off
Layout and marking1 dayEstablish suite locations

Deliverable: Space cleared and ready for framing

Weeks 7-9: Rough-In Work

Framing (Week 7-8):

ActivityDurationNotes
Metal stud framing4-5 daysAll suite walls
Door frame installation1-2 days18 suites + common
Bulkheads/soffits1-2 daysAs needed
Blocking for fixtures1 dayMirror, cabinet mounts

Rough Electrical (Week 7-8):

ActivityDurationNotes
Panel installation1 day200A panel
Branch circuit rough3-4 daysAll circuits
Outlet box installation2 daysPer suite requirements
Lighting rough2 daysBoxes and feeds

Rough Plumbing (Week 8-9):

ActivityDurationNotes
Drain rough-in2-3 daysBelow slab if needed
Supply rough-in2 daysHot and cold
Water heater1 daySet and connect
Vent connections1 dayPer code

HVAC Rough (Week 8-9):

ActivityDurationNotes
Ductwork3-4 daysSupply and return
Equipment setting1-2 daysAHU or mini-splits
Exhaust rough1 dayRestrooms, laundry

Milestone: Rough-In Inspection (End of Week 9)

  • Schedule trade inspections
  • Must pass before drywall
  • Payment trigger: 30%

Weeks 9-11: Insulation and First Drywall

ActivityDurationNotes
R-13 insulation installation2-3 daysAll suite walls
First drywall layer (base)3-4 daysBoth sides of all walls
Acoustic sealant application1 dayAll perimeters

Critical STC 48-52 Requirements:

  • Insulation fully fills cavity (no gaps)
  • Acoustic sealant at top track
  • Acoustic sealant at bottom track
  • Acoustic sealant around penetrations

Weeks 11-12: Green Glue and Second Drywall

ActivityDurationNotes
Green Glue application2 days2 tubes per 4x8 sheet
Second drywall layer (face)3-4 daysBoth sides of all walls
Taping2-3 daysFirst coat

Critical Requirements:

  • Green Glue covers full sheet (don't skip edges)
  • Second layer attached within 15 minutes of compound
  • No drywall joints aligned between layers

Weeks 12-13: Drywall Finishing

ActivityDurationNotes
Second coat mud2 daysAll joints
Third coat (if needed)1 daySand and touch-up
Sanding1-2 daysSmooth finish
Texture (if applicable)1 dayPer finish spec
Prime1-2 daysAll surfaces
Paint2-3 daysTwo coats

Weeks 13-14: Flooring Installation

ActivityDurationNotes
Subfloor prep1-2 daysLevel and clean
LVP installation (suites)3-4 days18 suites
LVP installation (common)1-2 daysCorridors, reception
Tile installation (restrooms)1-2 daysIf tile specified
Transitions and trim1 dayAll thresholds

Weeks 14-15: MEP Trim and Fixtures

Electrical Trim:

ActivityDurationNotes
Outlets and switches2-3 daysAll devices
Lighting fixtures2-3 daysTask, ambient, accent
Panel labeling1 dayPer suite

Plumbing Trim:

ActivityDurationNotes
Shampoo bowls2-3 days10-12 units
Faucets1 dayAll locations
Restroom fixtures1-2 daysToilets, sinks
Break room sink1 dayUtility sink

HVAC Trim:

ActivityDurationNotes
Diffusers and grilles1-2 daysAll locations
Thermostats1 dayZone controls
Exhaust fans1 dayRestrooms, laundry

Cabinetry and Millwork:

ActivityDurationNotes
Wall cabinets2-3 daysAll suites
Base cabinets1-2 daysShampoo areas
Mirrors1-2 daysAll styling stations

Weeks 15-16: Final Touches and Punch List

ActivityDurationNotes
Door hardware2 daysSmart lock prep (locks separate)
Touch-up paint1-2 daysAll surfaces
Cleaning1-2 daysConstruction clean
Punch list walk1 dayOwner + contractor
Punch list completion2-3 daysAddress all items

Milestone: Substantial Completion (End of Week 16)

  • All work complete except punch
  • Payment trigger: 30%

5. Closeout Phase (Weeks 16-18)

Inspection Schedule

WeekInspectionAuthorityNotes
W16Electrical finalCounty/InspectorAfter all devices complete
W16Plumbing finalCounty/InspectorAfter all fixtures complete
W16Mechanical finalCounty/InspectorAfter HVAC complete
W17Fire Marshal finalFire MarshalRequired for salon use
W17Building finalBuilding InspectorComprehensive review
W17-W18Certificate of OccupancyI&PAfter all finals pass

Inspection Preparation Checklist

Before Electrical Final:

  • All devices installed and operational
  • GFCI outlets tested
  • Panel labeled by suite
  • Emergency lighting functional
  • Exit signs illuminated

Before Plumbing Final:

  • All fixtures installed
  • No leaks at any connection
  • Hot water operational
  • Drain flow verified

Before Mechanical Final:

  • HVAC operational
  • Exhaust fans functional
  • Thermostats responding
  • Air balance acceptable

Before Fire Marshal Final:

  • Sprinklers unobstructed
  • Exit signage complete
  • Emergency lighting operational
  • Egress paths clear
  • Fire extinguishers mounted

Before Building Final:

  • All trade finals passed
  • ADA compliance verified
  • Finishes complete
  • Space clean and ready

Equipment Delivery and Installation (Week 18)

ActivityDurationNotes
China equipment receipt1 dayVerify against order
US equipment receipt1 dayShampoo bowls, etc.
Equipment staging1 dayOrganize by suite
Laundry equipment install1 dayWasher/dryer hookup
Final walkthrough1 dayOwner acceptance

Milestone: Certificate of Occupancy (Week 17-18)

  • Legal permission to occupy
  • Payment trigger: 10% (final)
  • Ready for tenant move-in

6. Critical Path Items

Critical Path Summary

The following items are on the critical path and any delay directly extends the project:

ItemStartDurationImpact if Delayed
Permit applicationWeek 23-6 weeks1:1 delay to construction
China equipment orderWeek 3-445+ daysTenant move-in delay
Fire Marshal coordinationWeek 5-6OngoingCO delay
Rough-in inspectionWeek 91-2 daysDrywall delay
Building final inspectionWeek 171-2 daysCO delay

Critical Path Visualization

CRITICAL PATH:

PERMIT APP (W2) -----> PERMIT REVIEW (W2-W8) -----> PERMIT ISSUE (W8)
                                                           |
                                                           v
                                                  CONSTRUCTION START (W8)
                                                           |
                                                           v
                                               ROUGH-IN COMPLETE (W9)
                                                           |
                                                           v
                                               INSPECTIONS (W9) -----> PASS
                                                                         |
                                                                         v
                                                              DRYWALL/FINISH (W9-W16)
                                                                         |
                                                                         v
                                                              SUBSTANTIAL COMP (W16)
                                                                         |
                                                                         v
                                                              FINAL INSPECTIONS (W16-W17)
                                                                         |
                                                                         v
                                                                     CO ISSUED (W18)

Float (Non-Critical) Activities

ActivityFloatNotes
Equipment selection2-3 weeksCan finalize during bidding
Furniture procurement4-6 weeksAfter major decisions
Signage6-8 weeksCan complete post-CO
IT/Security4-6 weeksCan parallel with construction

7. Milestone Markers

Payment Milestones

MilestonePercentageTrigger Criteria
Contract Signing30%Executed contract
Rough-In Complete30%All rough inspections passed
Substantial Completion30%Punch list walk complete
Final/CO10%CO issued, punch complete

Project Milestones

MilestoneTarget WeekTrigger
Lease ExecutedW0Project start
Design CompleteW1-2Floor plan and MEP approved
Contractor SelectedW3Contract signed
Permit SubmittedW2Application in system
China Order PlacedW3-4PO confirmed
Permit IssuedW6-8Building permit in hand
Construction StartW6-8Mobilization
Rough-In CompleteW9-10Inspections passed
Drywall CompleteW12-13Paint ready
Substantial CompletionW15-16Walk-through complete
Final InspectionsW16-17All trades passed
CO IssuedW17-18Legal occupancy
Equipment DeliveredW17-18All equipment on site
Tenant Move-In ReadyW18-20Fully operational

8. Timeline Scenarios

Optimistic Scenario: 13 Weeks

Assumptions:

  • Permit approved first review (no resubmittal)
  • No change orders
  • Weather/delivery issues none
  • Inspections pass first time
PhaseDuration
Pre-Construction2 weeks
Permits (parallel)3 weeks
Construction6 weeks
Closeout2 weeks
TOTAL13 weeks

Base Case Scenario: 18 Weeks

Assumptions:

  • One permit resubmittal required
  • Minor change orders
  • Standard inspection process
  • China shipping on schedule
PhaseDuration
Pre-Construction3 weeks
Permits5 weeks
Construction8 weeks
Closeout2 weeks
TOTAL18 weeks

Realistic/Conservative Scenario: 22 Weeks

Assumptions:

  • Two permit resubmittals
  • Moderate change orders
  • Fire Marshal additional review
  • China shipping delay (+2 weeks)
  • Weather contingency
PhaseDuration
Pre-Construction4 weeks
Permits6 weeks
Construction10 weeks
Closeout2 weeks
TOTAL22 weeks

Timeline Comparison Chart

SCENARIO      WEEK:  4   8  12  16  20  24
                     |---|---|---|---|---|
OPTIMISTIC           [=======|====CO====]     13 weeks
                     |---|---|---|---|---|
BASE CASE            [===========|========CO=====]    18 weeks
                     |---|---|---|---|---|
CONSERVATIVE         [================|============CO====]    22 weeks
                     |---|---|---|---|---|
              WEEK:  4   8  12  16  20  24

9. Contingency Planning

Schedule Contingencies

RiskProbabilityImpactMitigation
Permit delayMedium2-4 weeksEarly submission, pre-meeting with I&P
China shipping delayMedium2-3 weeksOrder early (Week 3), buffer in schedule
Material availabilityLow-Medium1-2 weeksConfirm lead times before ordering
Weather (delivery)Low1 weekIndoor staging area
Inspection failureLow-Medium1 weekPre-inspection walkthrough
Change ordersMedium1-3 weeksStrict change order control

Built-In Contingency Buffers

PhaseBase DurationBufferWith Buffer
Pre-Construction3 weeks+1 week4 weeks
Permits5 weeks+1 week6 weeks
Construction8 weeks+2 weeks10 weeks
Closeout2 weeks+0 weeks2 weeks
TOTAL18 weeks+4 weeks22 weeks

Contingency Recommendations

  1. Permit buffer: Add 2 weeks to permit timeline in all planning
  2. China shipping buffer: Add 2 weeks to quoted delivery dates
  3. Weather contingency: Plan deliveries mid-week (avoid Monday/Friday)
  4. Inspection buffer: Schedule inspections with 2-day cushion

10. Schedule Tracking Template

Weekly Progress Report Format

WeekPhasePlannedActualVarianceNotes
1Pre-ConDesign kickoff
2Pre-ConSOW distribution
3Pre-ConContractor selection
4PermitFirst review expected
.........

Milestone Tracking

MilestonePlanned DateActual DateVarianceStatus
Design Complete
Permit Submitted
Contractor Signed
Permit Issued
Rough-In Complete
Substantial Complete
CO Issued

Risk Log

RiskDate IdentifiedProbabilityImpactMitigationStatus

Construction Timeline Complete - Ready for Site-Specific Scheduling Phase 9: Build-Out Planning - Plan 01 Task 3 Complete